Weekly Project Update

Boones Ferry Rd at Avery Street

Thursday May 16th, the Boones Ferry / Avery signal will be shut down and traffic controlled by flaggers as the contractor activates the new traffic signal pole to accommodate a short right turn lane for eastbound traffic on Avery St turning right to head south on Boones Ferry Rd. Over the next couple of weeks the contractor will be widening the roadway for the new turn lane and pouring the new curb and sidewalk.  Expect delays 7am-4pm for the next couple of weeks.

More information is at www.boonesferrycorridor.com

Martinazzi Ave Sewer (Avery St to north of Sagert St)

Construction is planned to start in June to install a new sewer main under Martinazzi Avenue from Seminole Trail (north of Avery Street) to north of Sagert Street and repave this portion of Martinazzi Avenue and Sagert Street in the area of the recent traffic signal project and east to the Sagert St bridge over Interstate 5.  Martinazzi Avenue will be closed from Sagert Street to Avery Street for sewer work this summer.

Tualatin-Sherwood Rd and Nyberg St from Martinazzi to I-5

Pavement markings have been installed along eastbound Tualatin-Sherwood Road and Nyberg Street, and in the Cabela’s and Fred Meyer driveway approaches to Nyberg, to help drivers more easily see what lane to be in.

Thursday night May 9th, the contractor will add dotted lines to help westbound left-turners find the appropriate lane to travel south on Boones Ferry.

Sagert Court Paving

Thursday May 9th the contractor is planning to pave Sagert Court, a currently unpaved cul-de-sac south of Sagert Street, west of Boones Ferry Road

108th Avenue (Tualatin Rd to Leveton Dr)

A contractor for Lam Research is building frontage improvements along 108th Avenue in conjunction with development on the Lam Research site.

On Thursday May 9th the contractor will be installing new electrical conduit across Tualatin Road near 108th Ave.  Traffic will be controlled by flaggers; expect delays 9am-3pm.

67th, 68th Avenues and Sagert Street

The contractor has installed the remaining raised curbing and posts to provide a separate walkway/ bikeway on the Sagert Street bridge. 

Tualatin- Sherwood Rd (from Teton Ave to Sherwood)

Washington County’s contractor is adding travel lanes and pathways along Tualatin-Sherwood Rd from Teton Ave west into Sherwood.  They are also building a new 66” water line to carry Willamette River water to Beaverton, Aloha, and Hillsboro. They recently shifted traffic to the south side of the road and are now doing excavation and utility work along the north side of Tualatin-Sherwood Road for the widened roadway and pathway. 

More information is on the Washington County website at Tualatin-Sherwood Road (Langer Farms Parkway to Teton Avenue) | Washington County, OR (washingtoncountyor.gov)  and Road closure / traffic information at Road Closures & Traffic Advisories | WC-ROADS

Pavement Striping

The Public Works Department has a contractor refreshing the roadway striping (white and yellow lines, etc.) on streets around the City. 

Teton Ave Rail Crossing (Between Avery and Tualatin-Sherwood Road)

A contractor for the railroad plans to close Teton Avenue at its railroad crossing (between Avery Street and Tualatin-Sherwood Road) to replace the railroad crossing Friday July 7th to Monday morning July 10th.

Herman Rd (Tualatin Rd to Teton Ave)

The contractor is working along the north side of Herman Road connecting the irrigation system and doing final cleanup.

Plambeck Gardens - Boones Ferry Rd south of Norwood Rd

A developer is constructing the Plambeck Gardens affordable housing complex on the east side of Boones Ferry Road south of Norwood Road and south of Horizon Church. 

Autumn Sunrise Subdivision (Boones Ferry Road and Norwood Road)

A developer is constructing the 400-lot Autumn Sunrise subdivision stretching from Norwood Road west of Interstate 5 to Boones Ferry Road between Norwood and Day Roads.  The first phase homes near Norwood Road are nearing completion and becoming occupied, the second phase of homes are under construction, and the developer is building the road, water, sewer, and storm drainage infrastructure for the third phase nearest Boones Ferry Road.

Reservoir and Pump Station at Aquifer Storage and Recovery (ASR) Site

The City is reviewing proposals this week from professional Engineering firms to design a new reservoir and pump station at the aquifer storage and recovery (ASR) site in the Ibach neighborhood.  This will provide additional water storage and service capacity for the southern part of Tualatin.

 

Click to view older weekly project updates

 

 

Updated: 5/10/2024

 

To download a printable copy of previous project updates see attachments below.

Click any thumbnail image to view a slideshow

Sidewalk improvement
Crosswalk improvement
Sidewalk stamps
Road Construction